Amended notice of road closure, Cromwell Lane-Burton Green
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-46-14/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Burton Green
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 30/10/2023
- Estimated End Date
- 25/11/2023
What we are doing
Updated notice
We are not expecting to undertake the second phase.
As part of our final realignment works on Cromwell Lane, we are required to carry out further programme of utility works on Cromwell Lane. To safely carry out the work we will need to close Cromwell Lane to create a safe working environment.
These works will be carried out in 2 phases.
Phase one works will start from 30 October to 25 November 2023.
Phase two works will start 04 December 2023 to 16 December 2023.
Please note that a closure will be in place 24 hours a day while these works are carried out. A fully signposted diversion will be in place throughout the closure with access to all properties maintained throughout. Cromwell Lane will remain open for pedestrians and cyclists.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk