Notice of full road closure, Dalehouse Lane, Kenilworth
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-27-20/04/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Kenilworth
- Contractor
- BBV JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 11/09/2023
- Estimated End Date
- 01/12/2023
What we are doing
***UPDATE***
Works on phase one of the closure have over-run and Dalehouse Lane will will re-open by 1pm on Saturday 7 October.
We will be carrying out temporary utility diversion and connection works to facilitate the construction of the new overbridge.
To ensure public safety and for the works to be carried out safely, a full road closure will be in place for 24 hours for the duration of the works.
Our works will run from 11 September to 1 December 2023. and will be carried out in two phases.
Phase 1: 11 September to 6 October 2023
Phase 2: 6 November to 1 December 2023
Our working hours will be 8am to 6pm, Monday to Friday.